Nyanzaga Mine strikes gold at TMIC 2026 as it readies for its production

DAR ES SALAAM: AFTER 17 years of exploration and construction, the Nyanzaga Gold Project has participated in the Seventh Tanzania Mining and Investment Conference (TMIC 2026) as a new investor preparing to join Tanzania’s gold-producing sector, with first gold pour targeted for January 2027.
The project, located in Sengerema District, Mwanza Region, is being developed by Sotta Mining Corporation Limited, a joint venture between Perseus Mining, which holds an 80 per cent stake, and the Government of Tanzania, which owns the remaining 20 per cent.
Nyanzaga’s journey began with exploration in the Lake Victoria gold belt, followed by years of drilling, studies, permitting and engagement with the Government. Perseus Mining acquired the project in 2024 and made its Final Investment Decision in April 2025.
Since then, the project has been connected to the national electricity grid, secured water supply from Lake Victoria, handed over houses to families relocated to pave the way for the project and advanced construction of its processing plant.
Between July 2024 and March 2026, Nyanzaga generated a direct economic contribution of 457.7bn/- to Tanzania, including 371.6bn/- spent on local suppliers and 60.7bn/- paid to the government.
More than 3,600 people are currently working at the project site, including 281 direct employees, the majority of whom are Tanzanians. The project has also provided 202 training opportunities, community water infrastructure, a replacement primary school and a new dispensary.
The company has worked closely with the Ministry of Minerals, the Mining Commission and other regulatory institutions, while participating in industry platforms, including previous editions of TMIC.
Speaking during the Seventh Tanzania Mining and Investment Conference (TMIC 2026) in Dar es Salaam, Country Manager Isaac Lupokela said the company had participated as a key stakeholder in the mining sector as it prepares to commence production.
ALSO READ: Tanzania lures more investors to establish mineral processing, value addition industries
“Nyanzaga has been under development for 17 years,” Mr Lupokela said. “As we approach our first gold pour in January 2027, we are participating in TMIC as an active new player in the sector. The first gold pour will demonstrate that Tanzania’s mineral resources remain viable and beneficial to the nation.”
Nyanzaga will become Perseus Mining’s fourth gold mine in Africa and is expected to produce an average of more than 200,000 ounces of gold annually from the 2028 to 2035 financial years.